EPC B by 2031: a five-stage plan for getting there

10th November 2026
Property management - Heals Building
Property management - Heals Building
Hedley Jones Head of Sustainability, Refurbishment & Development
Hedley Jones
Head of Sustainability, Refurbishment & Development

With EPC B confirmed as the bar for larger commercial buildings by 2031, and no interim hurdle on the way, landlords finally have a fixed target to plan towards.

Property managers and asset managers can now work back from that date to shape one coherent upgrade programme, timed around the building’s own lease events and investment cycle, writes Hedley Jones, Partner and Head of Sustainability Refurbishment and Development.

A fixed end point to plan towards

Five years of policy limbo finally ended in June when the Department for Energy Security and Net Zero (DESNZ), published its response to the long-running consultation on strengthening Minimum Energy Efficiency Standards (MEES) for the non-domestic private rented sector.

From 2031, privately rented commercial buildings over 1,000 square metres in England and Wales will need to reach an EPC rating of B. Buildings below that threshold stay on the current EPC E minimum, with no fixed deadline to go further. The seven-year payback test and existing exemption mechanisms remain in place, so only works that genuinely pay for themselves in energy savings will be required.

For an industry that has spent years planning around a moving target, the most significant outcome of the interim response is certainty. Landlords now know exactly where the statutory bar sits, EPC B for buildings over 1,000 square metres, and exactly when they need to clear it: 2031. That clarity is what makes proper planning possible.

Most landlords of larger, weaker-performing assets were already assuming they’d need to reach B eventually. What they lacked was a fixed end point to plan towards, and confirmation that there would be no interim hurdle along the way. They now have both. The EPC C milestone originally pencilled in for 2027 has been dropped, and that decision is being read across the property world as a highly practical win.

The 2027 milestone would have forced landlords into a messy, two-stage upgrade: spend now to nudge a building from D or E up to C, then spend again a few years later to push on to B. That would have front-loaded cost and meant specifying and installing measures that get ripped out or superseded before their useful life is up. It would also rarely have lined up with when a building is under-occupied enough to do the work properly.

With one target and one date, the planning task becomes far more straightforward. Property managers and asset managers can work back from B in 2031 to build a single, comprehensive energy efficiency strategy over the next five years, rather than two disruptive phases squeezed into a shorter window. And, crucially, they can align that plan with lease events that were going to happen anyway.

So that’s the opportunity. The harder question is what to actually do with it, and how to make it work commercially. Clarity is only valuable if it’s used to build a better plan, not simply to defer thinking. Below are the five stages asset managers and property investors should be setting out:

1. Assess the baseline

Every plan starts with an honest picture of where the building stands today. That means the current EPC rating and what’s driving it, but also actual metered energy performance, condition of the core building services, and how far the asset is from a B rating in practice, rather than on paper. For a portfolio, this is also the moment to identify which assets sit over the 1,000 square metre threshold and are therefore in scope, and which are furthest from compliance and likely to need the most lead-in time. The overarching baseline should be to optimise what you already have.

2. Layer sustainability into the PPM, and build the plan into the investment strategy

Rather than treating decarbonisation as a bolt-on project, the most effective approach overlays sustainability measures onto the existing planned preventative maintenance schedule. Instead of a like-for-like replacement of, say, a gas boiler at end of life, the PPM overlay flags the low-carbon alternative alongside it, with costs identified separately so all parties can see, and discuss, the trade-off transparently.

Layered up over several PPM cycles, this becomes a genuine investment plan, and part of the asset business plan, rather than competing with it for budget.

3. Map the works against lease events and the business plan

This is where the extra time really pays off. Rather than working to an arbitrary regulatory date, the plan can now be built around the building’s own natural rhythm: lease expiries, breaks, refurbishment cycles and void periods. Disruptive works can be scheduled when floors are empty, or plans made to rotate occupiers while more intrusive works are taking place.

Capital can be phased to match the fund or asset’s own investment cycle rather than forced into an artificial short-term window. However, be aware that the five-year runway may not be enough time if lease events and current plant lifecycle goes beyond this.

4. Sequence and prioritise, but crack on anyway

Secondary legislation still needs to pass through Parliament, and the detail may yet move again, but the direction of travel is clear enough to act on now. There’s no reason to wait. The task is to decide what needs doing immediately; data gathering, optimising existing controls and setpoints, addressing the biggest, easiest wins, versus what can be sequenced later without boxing the building into a corner.

This is genuinely the difficult part. Everyone in the industry already knows a gas boiler will eventually need replacing with a heat pump or electric alternative; that’s not a hard call. The hard call is timing it correctly: late enough to capture the full remaining life of the existing plant and avoid wasting embodied carbon, but early enough that it doesn’t collide with a lease event, a refurbishment, or a funding cycle. Getting the “what” right is easy. Getting the “when” and “how” right within the constraints of the business plan is where the value is created.

5. Monitor, verify, and stay flexible

Once works are under way, the plan needs a feedback loop: metered data to confirm the measures are delivering the expected savings, and reporting that keeps pace with what investors, lenders and occupiers now expect. Because the legislation is not yet finalised, the plan also needs to retain some flexibility to adjust as further detail emerges from government, without unravelling the underlying strategy.

What matters is the sequencing

Taken in isolation, none of these five stages is complicated. What matters is the sequencing and the discipline of doing them in the right order, rather than reacting piecemeal to whichever measure looks most urgent this quarter.

The regulatory reset hasn’t changed what good asset management looks like, it has simply removed an artificial deadline that was forcing decisions to be made badly.

Landlords and their managing agents now have the breathing space to make decisions, putting the asset in a stronger position for the long term, not just for the next compliance deadline.

We help clients improve sustainability performance across the lifecycle of commercial property assets.

Explore our Sustainability Asset Plans